TO MAKE A SQUARE - 02


AIM: TO MAKE A SQUARE

TOOLS REQUIRED:

1. STEEL RULE
2. SCRIBER, DOT PUNCH
3. HACK SAW BLADE AND FRAME
4. BALL PEEN HAMMER
5. TRY SQUARE
6. 12" BASTARD FLAT FILE
7. 6" SMOOTH FLAT FILE

MATERIALS REQUIRED

1. 50 x 50 x 6 M. S. FLAT
2. MARKING BLUE
3. CLEANING BRUSH

PROCEDURE:

1. INITIALLY CUT OFF THE WORK PIECE FROM RAW MATERIAL BY USING A HACK SAW FRAME AND A BLADE. THE MARKING IS DONE BY A SCRIBER AND STEEL RULE.

2. THEN DEBURR ALL THE EDGES BY USING A FILE.

3. AFTER DEBURRING HOLD THE JOB ON THE BENCH VICE TIGHTLY.

4. THEN FILE ANY ONE EDGE TO BECOME FLAT. IT IS CHEECKED BY USING A TRY SQUARE. ALSO THE FILING IS DONE BY BOTH 6" AND 12" FLAT FILES.

5. THEN FILE THE ADJACENT SIDE MUTUALLY PERPENDICULAR TO EACH OTHER BY USING 12" BASTARD FLAT FILE. THE PERPENDICULARITY WAS CHECKED BY A TRY SQUARE.

6. AFTER COMPLETING THE DATUM SIDES, MARK THE LENGTH AND HEIGHT OF 45mm. BY USING A VERNIER HEIGHT GAUGE. ALSO APPLY THE MARKING BLUE INTO THE SURFACES OF JOB FOR BETTER CLARITY.

7. THEN PUNCH THE MARKED LINES BY USING A DOT PUNCH AND BALL PEEN HAMMER.

8. AFTER MARKING, CUT OFF THE UN-WANTED AREA BY USING HACK SAW FRAME AND BLADE.

9.THEN FILE THE OTHER TWO SIDES MUTUALLY PERPENDICULAR TO EACH OTHER BY USING A 12" BASTARD FLAT FILE.

10. AT LAST THE FINISHING FILING WAS DONE BY 6" SMOOTH FLAT FILE FOR GETTING SMOOTH SURFACES.

11. THEN SUBMIT THE WORK PIECE FOR INSPECTION, AFTER 1mm. CHAMFERING AND DEBURRING.

RESULT:

 THE FILING OF SQUARE IS DONE SUCCESSFULLY AS PER THE DIMENSIN OF 5mm. THICK AND SIDES OF 45mm. LENGTH